CSO: 1B3b LOS: 1B3e Martin Fabricating uses a cumulative average-time learning curve model to monitor labor costs. Data regarding two recently completed batches of a part that is used in tractor-trailer rigs is as follows. If the same rate

CSO: 1B3b LOS: 1B3e
Martin Fabricating uses a cumulative average-time learning curve model to monitor labor costs. Data regarding two recently completed batches of a part that is used in tractor-trailer rigs is as follows.


If the same rate of learning continues for the next several batches produced, which of the following best describes (1) the type (i.e., degree) of learning curve that the firm is experiencing and (2) the average hours per unit for units included in the 201-400 range of units produced (i.e., the last 200 units)?
 

 



微信扫一扫,获取CMA最新资讯,官方真题,在线咨询,资料等等。。。
TEL:400-1818-193 CMA分享与交流QQ群:639110877  
★★★点击免费领取CMA考试实战练习题★★★
CMA高清网课地址点击体验

热门搜索词: CMA培训. CMA考试. CMA考题讲解. CMA资料.

编辑推荐:
全方位保障通过率
相关资讯:
  • CMA考试
  • 了解CMA
在线视频
您可能感兴趣
  • 文章
  • 专题
  • 热门
  • 活动